Wharton Data Center Firewall Update 1/4/24
Scheduled Maintenance Report for Wharton Computing
Completed
The scheduled maintenance has been completed.
Posted Jan 04, 2024 - 08:01 EST
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Jan 04, 2024 - 06:00 EST
Scheduled
On Thursday January 4, from 6am – 8am, the Wharton Data Center Firewall will be updated. During this time, any connections using the firewall will be interrupted. This includes your ability to log into your Wharton-managed PC or laptop.

Once the update is complete, your connection should be re-established automatically. If this does not work, however, try logging in again. We expect the interruption of service to last approximately 30 minutes.

Please contact your Wharton Computing representative if you have any questions about the update.
Posted Dec 22, 2023 - 12:10 EST
This scheduled maintenance affected: Labs (F80, F75, 380, 375), Web (Wharton Custom Applications), and High Performance Computing Cluster, Student Printing, Virtual Lab.